Islamabad Safe City project will now cost Rs. 14.8 billion

The cost of Islamabad Safe City Project has increased by 25% after the Federal Board of Revenue (FBR) refused to grant tax exemption to the imported equipment for the project. This has taken the cost of the project up to Rs 14.865 billion, adding Rs. 3 billion to the previous cost estimation of the project which was Rs. 11.865 billion.

The equipment for the project has already arrived, and the Interior Ministry has been paying the storage and demurrage charges since March this year. The taxes and duties were not accounted at the time of inception of Safe City Project considering security related projects in which exemption are generally granted by FBR and Ministry of Finance. The Islamabad Safe City Project was officially inaugurated in June this year and the National Database and Registration Authority (NADRA) was tasked with implementing the project back in March.

The main aim of the project is to ensure the protection of the citizens of the capital. This will be achieved by creating an effective and adequate security framework by incorporating strategies preventing unauthorised access of vehicles and individuals entering and operating within the federal capital. Basically, this foresees a sharper monitoring and surveillance system.

The project will promote the use of smart ID cards, Electronics RFID tags, Smart Vehicle Registration and Smart Driver Licence for authentication of vehicles and individuals. CCTV cameras and RFID tag readers will be installed at key points across the city, to provide an effective monitoring and control system. The project will equip law enforcement agencies with a computer aided dispatch system and other software such as facial recognition and vehicle management system.

Under the plan close to 1950 surveillance cameras will be installed in the capital along with a bombproof command centre of 2000 square meters, to which all the cameras would be connected through 500kms of fiber optic cable, operated through a 4G network.

The project was first approved in 2011 but was challenged by the Supreme Court and after an ugly battle the contract was struck down in 2012. After PML-N’s rise to power, the project was reconsidered. China is paying the greater part of the entire project while the Pakistani government is expected to pay only the recent Rs. 3 billion addition to the cost.

-Source The Nation

Sponsored
Maryam Dodhy

I love bringing to light stories of extraordinary people working in Pakistan's tech and startup industry. You can reach out to me through maryamdodhy@techjuice.pk.

Leave a Comment
Share
Published by
Maryam Dodhy

Recent Posts

Indian Army Granted Authority to Directly Takedown Social Media Content

The Indian Army has been granted direct authority to manage social media content concerning its…

8 hours ago

NUST Achieves Global Recognition with 43 Researchers Among World’s Top 2% Scientists

In an extraordinary accomplishment for Pakistani academia, 43 researchers from the National University of Sciences…

9 hours ago

Khyber Pakhtunkhwa Govt Ready to Acquire PIA with Bid Exceeding Rs10bn

The Khyber Pakhtunkhwa (KP) government has officially informed the federal government of its intention to…

11 hours ago

PTA Cautions Public on Illegal and Unlicensed Forex Trading Platforms

The Pakistan Telecommunication Authority (PTA) has issued a stern advisory, warning citizens against investing in…

11 hours ago

Record Emigration: Economic Instability Forces Pakistan’s Best and Brightest to Depart

Economic challenges are prompting skilled workers to leave Pakistan, resulting in a significant talent drain…

13 hours ago

Russia’s Fine on Google Exceeds World’s Economy

A Russian court has fined Google for blocking state-run media channels on YouTube, imposing a…

1 day ago